Snapshot: Demolition and Debris Removal Progress

747K cubic yards of debris removed from right of way 

1,400-1,600 total demolitions estimated

700+ demolitions completed in phase 1

$33M invested in phase 1 demolitions

$30-45M still needed to finish demolitions

We remove unsafe, tornado-damaged buildings so every block is safe and ready to rebuild.

Track Demolition Progress

With thousands of demolitions in our pipeline, take a look at where work is happening through our online progress tracker. Search an address to see whether a building is scheduled, in progress or complete.

Screenshot 2026-11-08 223152

THREE PHASES OF WORK

Phase 1 made blocks safe. Phase 2 finishes that job. Phase 3 ties demolition to rebuilding.

A blue arrow icon pointing right containing a yellow circle with a checkmark.

PHASE 1: EMERGENCY
May 2025–December 2026

MAKE EVERY BLOCK SAFE.

Current Focus Areas:

700+ Demolitions

Building that collapsed or poses an immediate safety threat
Damaged structures on high-traffic corridors
Owner-requested demolitions

Work pauses in December, except emergencies, while remaining work and permits close out.

Additional actions included:

Emergency debris removal and street clearing
Initial property damage assessments
Hazardous tree and limb removal

How Phase 1 was funded
More than $30 million from every level of government.

City and local · $11M

Board Bill 22 (Rams settlement) $7M, General Revenue through the Building Division $3M, MSD $1M

State · $10M

Missouri Senate Bill 1

Federal · $12M

ARPA through the Land Reutilization Authority $6M, State-managed FEMA debris removal $4M, City-managed FEMA demolition $2M

A blue arrow icon pointing right containing a white gear symbol surrounded by a yellow dashed circle.

PHASE 2: PRIORITY
JANUARY 2027+

FINISHING THE JOB.

Future Focus Areas:

Remaining emergency, corridor and owner-requested demolitions
Collapsed or dangerous priority structures
Clean-up of remaining hardscape and vegetation on cleared lots
Debris not eligible for FEMA funding
Demolitions near major rebuilding projects
A blue arrow icon pointing right containing a yellow circle with a checkmark.

PHASE 3: REBUILDING

CLEARING THE WAY TO REBUILD.

Future focus areas:

Demolitions tied to economic recovery and rebuilding
Coordinated with home repair and new investment
Guided by resident-led neighborhood plans
IMG_4823

How a Demolition Happens

Every property goes through the same steps.

STEP 1:

Owner or City Initiation
For owner-requested demolitions, a Right of Entry is secured and property ownership is verified. The City may also initiate demolition when a structure poses a public safety threat.

 

STEP 2:

Inspection
The Building Division assesses the structure's condition and determines if demolition is necessary.

 

STEP 3:

Condemnation
Unsafe structures are condemned through either (1) emergency condemnation (not appealable) or (2) structural condemnation (10-day appeal window). Property owners are notified of the condemnation.

 

STEP 4:

Funding and scheduling
Each property is assigned a funding source, demolition phase, contractor batch, and priority ranking. Priority is given to public safety threats, followed by properties on densely populated blocks.

 

STEP 5:

Demolition
Electric and gas utilities are disconnected, the structure is safely taken down.

 

STEP 6:

Lot Clean-Up
Debris is removed, the site is backfilled, and grass seeds and straw are applied to the lot.

 

Demolition: Health & Safety Tips for Awareness

As our crews work to safely remove these buildings, we want to prepare residents for temporary impacts like noise, dust, street closures, and increased truck traffic in affected neighborhoods. Visit the City Government site to understand health impacts and precautions to be aware of during the demolition of buildings.

IMG_5873

Demolition Program: Common Questions

Why is working pausing in December 2026?

Our team is closing out Phase 1 work and permits, while preparing for Phase 2 and finalizing full funding to ensure smooth operations. Emergency demolitions will continue as needed.

A building near me looks dangerous. Who do I call?

Check our online dashboard HERE.
If not on the list or is on the list and not showing as planned or underway, but an emergency, call the Resident Support Team at 314-207-7395.

How do I know when a property will be demolished?

Use the map above to check the demolition status of a specific property. For Planned demolitions, permits and inspections may take approximately 1–3 months to complete. Once a demolition is In Progress, work is typically completed within 3–6 weeks.

I own a damaged building. What are my options?

Call the Resident Support Team at 314-207-7395 to schedule an appointment with our team to talk through repair, owner-requested demolition, and other options.